For an activity with more than one immediate successor activity, its latest-finish time is equal to the
a. largest latest-finish time among its immediate successors.
b. smallest latest-finish time among its immediate successors.
c. largest latest-start time among its immediate successors.
d. smallest latest-start time among its immediate successors.
Question 2
In a regression analysis, the variable that is used to predict the dependent variable ______.
a. must have the same units as the variable doing the predicting
b. is the independent variable
c. is the dependent variable
d. usually is denoted by x
-
Answer to Question 1
D
Answer to Question 2
b