Title: For an activity with more than one immediate successor activity, its latest-finish time is equal to ...
Post by: Bernana on Jun 24, 2018
For an activity with more than one immediate successor activity, its latest-finish time is equal to the
 a. largest latest-finish time among its immediate successors.
  b. smallest latest-finish time among its immediate successors.
  c. largest latest-start time among its immediate successors.
  d. smallest latest-start time among its immediate successors.

Question 2

In a regression analysis, the variable that is used to predict the dependent variable ______.
 a. must have the same units as the variable doing the predicting
  b. is the independent variable
  c. is the dependent variable
  d. usually is denoted by x
Title: For an activity with more than one immediate successor activity, its latest-finish time is equal to ...
Post by: Eunice618 on Jun 24, 2018
Answer to Question 1

D

Answer to Question 2

b