Author Question: Suppose you have the following project digraph. (The numbers in parentheses represent hours.)The ... (Read 341 times)

audragclark

  • Hero Member
  • *****
  • Posts: 579

Question 1

Suppose you have the project consisting of the six tasks described in the following table.




Which project digraph below models the project described?












◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The number of tasks in the project is
◦ 8.
◦ 6.
◦ 9.
◦ 7.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by audragclark on May 5, 2020

xthemafja

  • Sr. Member
  • ****
  • Posts: 348
Lorsum iprem. Lorsus sur ipci. Lorsem sur iprem. Lorsum sur ipdi, lorsem sur ipci. Lorsum sur iprium, valum sur ipci et, vala sur ipci. Lorsem sur ipci, lorsa sur iprem. Valus sur ipdi. Lorsus sur iprium nunc, valem sur iprium. Valem sur ipdi. Lorsa sur iprium. Lorsum sur iprium. Valem sur ipdi. Vala sur ipdi nunc, valem sur ipdi, valum sur ipdi, lorsem sur ipdi, vala sur ipdi. Valem sur iprem nunc, lorsa sur iprium. Valum sur ipdi et, lorsus sur ipci. Valem sur iprem. Valem sur ipci. Lorsa sur iprium. Lorsem sur ipci, valus sur iprem. Lorsem sur iprem nunc, valus sur iprium.
Answer Preview
Only 50% of students answer this correctly



maychende

  • Hero Member
  • *****
  • Posts: 556

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The number of tasks in the project is
◦ 7.
◦ 9.
◦ 8.
◦ 10.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




What is the number of tasks in this project?
◦ 11
◦ 9
◦ 6
◦ 7
◦ none of these




ts19998

  • Hero Member
  • *****
  • Posts: 531
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the priority list, C, F, E, B, A, D and the priority-list model to schedule this project with two processors results in a finishing time of
◦ 22 hours.
◦ 18 hours.
◦ 23 hours.
◦ 19 hours.
◦ none of these




burchfield96

  • Hero Member
  • *****
  • Posts: 610
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the priority list, C, E, G, F, B, A, D and the priority-list model to schedule this project with two processors results in a finishing time of
◦ 24 hours.
◦ 21 hours.
◦ 26 hours.
◦ 22 hours.
◦ none of these




misspop

  • Hero Member
  • *****
  • Posts: 540
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the priority list F, E, A, D, B, G, C and the priority-list model to schedule this project with two processors, the project finishing time is
◦ 22 hours.
◦ 17 hours.
◦ 18 hours.
◦ 21 hours.
◦ none of these




 

Did you know?

Women are 50% to 75% more likely than men to experience an adverse drug reaction.

Did you know?

Carbamazepine can interfere with the results of home pregnancy tests. If you are taking carbamazepine, do not try to test for pregnancy at home.

Did you know?

IgA antibodies protect body surfaces exposed to outside foreign substances. IgG antibodies are found in all body fluids. IgM antibodies are the first type of antibody made in response to an infection. IgE antibody levels are often high in people with allergies. IgD antibodies are found in tissues lining the abdomen and chest.

Did you know?

In 1835 it was discovered that a disease of silkworms known as muscardine could be transferred from one silkworm to another, and was caused by a fungus.

Did you know?

Egg cells are about the size of a grain of sand. They are formed inside of a female's ovaries before she is even born.

For a complete list of videos, visit our video library