Title: When using the beta distribution for estimating activity times:
Post by: pepyto on Apr 18, 2020
When using the beta distribution for estimating activity times:
◦ the most likely time estimate can be positioned anywhere between the optimistic and pessimistic time estimates.
◦ we assume that the standard deviation is one-third the range between the optimistic and pessimistic time estimates.
◦ the most likely time estimate becomes the mean of the distribution.
◦ an advantage is that the mode of the distribution is always equidistant from the end points of the distribution.
Title: When using the beta distribution for estimating activity times:
Post by: jsm54321 on Apr 18, 2020
the most likely time estimate can be positioned anywhere between the optimistic and pessimistic time estimates.
Title: Re: When using the beta distribution for estimating activity times:
Post by: Nico Estrada on Aug 8, 2022
Thank You