Title: A manager budgeted $60,000 in revenue and a 20% beverage cost for an accounting period. The manager ...
Post by: Evvie72 on Aug 15, 2020

Question 1

A manager budgeted $3000 for repair expense. The manager's actual repair expense was $3450. What was this manager's variance percentage for repair expense?
◦ 5%
◦ 10%
◦ 15%
◦ 20%

Question 2

A manager budgeted $60,000 in revenue and a 20% beverage cost for an accounting period. The manager achieved $60,000 in revenue for the period but generated a 22% beverage cost. What was the dollar amount of the manager's beverage cost variance?
◦ $9000
◦ $10,000
◦ $11,000
◦ $12,000
Title: A manager budgeted $60,000 in revenue and a 20% beverage cost for an accounting period. The manager ...
Post by: akemokai on Aug 15, 2020

Answer 1

15%

Answer 2

$12,000