Question 1

Complete the table, find average lateness, find average completion time, and average number of jobs in the system. Assume all durations are in days and that the jobs are processed at the shop in the order that they arrive (A then B then C then D).

JobProcess TimeFlow TimeDue DateLateness
A5
B39
C212
D54
Sum (Average)15 (3.75)XXXXX


Question 2

TPS stands for Toyota Production System.
◦ true
◦ false
Title: TPS stands for Toyota Production System.
Post by: Rilsmarie951 on Dec 3, 2019

Answer 1


JobProcess TimeFlow TimeDue DateLateness
A5570
B3890
C210120
D515411
Sum (Average)15 (3.75)38 (9.5)XXXXX11 (2.75)

Avg lateness = 11/4 = 2.75 days
Avg completion time = 38/4 = 9.5 days
Avg number of jobs in the system = 38/15 = 2.53 jobs

Answer 2

true