Author Question: Suppose you have the following project digraph. (The numbers in parentheses represent hours.)The ... (Read 350 times)

audragclark

  • Hero Member
  • *****
  • Posts: 579

Question 1

Suppose you have the project consisting of the six tasks described in the following table.




Which project digraph below models the project described?












◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The number of tasks in the project is
◦ 8.
◦ 6.
◦ 9.
◦ 7.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by audragclark on May 5, 2020

xthemafja

  • Sr. Member
  • ****
  • Posts: 348
Lorsum iprem. Lorsus sur ipci. Lorsem sur iprem. Lorsum sur ipdi, lorsem sur ipci. Lorsum sur iprium, valum sur ipci et, vala sur ipci. Lorsem sur ipci, lorsa sur iprem. Valus sur ipdi. Lorsus sur iprium nunc, valem sur iprium. Valem sur ipdi. Lorsa sur iprium. Lorsum sur iprium. Valem sur ipdi. Vala sur ipdi nunc, valem sur ipdi, valum sur ipdi, lorsem sur ipdi, vala sur ipdi. Valem sur iprem nunc, lorsa sur iprium. Valum sur ipdi et, lorsus sur ipci. Valem sur iprem. Valem sur ipci. Lorsa sur iprium. Lorsem sur ipci, valus sur iprem. Lorsem sur iprem nunc, valus sur iprium.
Answer Preview
Only 50% of students answer this correctly



maychende

  • Hero Member
  • *****
  • Posts: 556

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The number of tasks in the project is
◦ 7.
◦ 9.
◦ 8.
◦ 10.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




What is the number of tasks in this project?
◦ 11
◦ 9
◦ 6
◦ 7
◦ none of these




ts19998

  • Hero Member
  • *****
  • Posts: 531
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the priority list, C, F, E, B, A, D and the priority-list model to schedule this project with two processors results in a finishing time of
◦ 22 hours.
◦ 18 hours.
◦ 23 hours.
◦ 19 hours.
◦ none of these




burchfield96

  • Hero Member
  • *****
  • Posts: 610
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the priority list, C, E, G, F, B, A, D and the priority-list model to schedule this project with two processors results in a finishing time of
◦ 24 hours.
◦ 21 hours.
◦ 26 hours.
◦ 22 hours.
◦ none of these




misspop

  • Hero Member
  • *****
  • Posts: 540
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the priority list F, E, A, D, B, G, C and the priority-list model to schedule this project with two processors, the project finishing time is
◦ 22 hours.
◦ 17 hours.
◦ 18 hours.
◦ 21 hours.
◦ none of these




 

Did you know?

More than 150,000 Americans killed by cardiovascular disease are younger than the age of 65 years.

Did you know?

The average human gut is home to perhaps 500 to 1,000 different species of bacteria.

Did you know?

The eye muscles are the most active muscles in the whole body. The external muscles that move the eyes are the strongest muscles in the human body for the job they have to do. They are 100 times more powerful than they need to be.

Did you know?

Though “Krazy Glue” or “Super Glue” has the ability to seal small wounds, it is not recommended for this purpose since it contains many substances that should not enter the body through the skin, and may be harmful.

Did you know?

This year, an estimated 1.4 million Americans will have a new or recurrent heart attack.

For a complete list of videos, visit our video library