Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with two processors, the project finishing time is
◦ 20 hours.
◦ 18 hours.
◦ 17 hours.
◦ 19 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with two processors, the total combined idle time of the two processors is
◦ 5 hours.
◦ 3 hours.
◦ 7 hours.
◦ 1 hour.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

samiel-sayed

  • Sr. Member
  • ****
  • Posts: 337

itsmyluck

  • Hero Member
  • *****
  • Posts: 546

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with three processors, the project finishing time is
◦ 12 hours.
◦ 13 hours.
◦ 11 hours.
◦ 14 hours.
◦ none of these

Question 2

A project consists of five tasks. The lengths of the tasks (in hours) are 5, 4, 4, 3, and 3. The tasks are all independent (i.e., there are no precedence relations).

Using the critical-path algorithm to schedule the project with two processors, the finishing time is
◦ 12 hours.
◦ 9 hours.
◦ 10 hours.
◦ 11 hours.
◦ none of these



olderstudent

  • Sr. Member
  • ****
  • Posts: 339

 

Did you know?

Serum cholesterol testing in adults is recommended every 1 to 5 years. People with diabetes and a family history of high cholesterol should be tested even more frequently.

Did you know?

For about 100 years, scientists thought that peptic ulcers were caused by stress, spicy food, and alcohol. Later, researchers added stomach acid to the list of causes and began treating ulcers with antacids. Now it is known that peptic ulcers are predominantly caused by Helicobacter pylori, a spiral-shaped bacterium that normally exist in the stomach.

Did you know?

Essential fatty acids have been shown to be effective against ulcers, asthma, dental cavities, and skin disorders such as acne.

Did you know?

Intradermal injections are somewhat difficult to correctly administer because the skin layers are so thin that it is easy to accidentally punch through to the deeper subcutaneous layer.

Did you know?

Common abbreviations that cause medication errors include U (unit), mg (milligram), QD (every day), SC (subcutaneous), TIW (three times per week), D/C (discharge or discontinue), HS (at bedtime or "hours of sleep"), cc (cubic centimeters), and AU (each ear).

For a complete list of videos, visit our video library