Title: A line-balancing solution has been developed for the assembly line for fertilizer spreaders at Green ...
Post by: hubes95 on Apr 18, 2020
A line-balancing solution has been developed for the assembly line for fertilizer spreaders at Green Grass, Inc. The desired output rate of 30 spreaders per hour will be achieved. The sum of times for all tasks performed on the line is 1200 seconds for each spreader assembled. This is the total productive time. Which of the following statements must be true?
◦ If the solution calls for 11 stations, the efficiency is 80%.
◦ If the solution calls for 12 stations, the efficiency is 80%.
◦ The theoretical minimum number of stations is 10.
◦ The cycle time is 30 seconds per spreader.
Title: A line-balancing solution has been developed for the assembly line for fertilizer spreaders at Green ...
Post by: stallen on Apr 18, 2020
The theoretical minimum number of stations is 10.
Title: Re: A line-balancing solution has been developed for the assembly line for fertilizer spreaders at G
Post by: Teek Tim on Jun 13, 2021
thank you
Title: Re: A line-balancing solution has been developed for the assembly line for fertilizer spreaders at G
Post by: Vipul Bhatnagar on Jun 25, 2021
Thank you