Title: ________ is a tangible benefit of information systems. A) Improved asset usage B) Reduced ...
Post by: P68T on Jul 7, 2018
________ is a tangible benefit of information systems.
 
  A) Improved asset usage
  B) Reduced workforce
  C) Better corporate image
  D) More information
  E) Improved resource control

Question 2

A PERT chart:
 
  A) portrays a project as a network diagram consisting of numbered nodes that represent tasks.
  B) is used to evaluate project risk and time.
  C) displays a horizontal bar for each project task.
  D) tracks progress of, and modifications to, project tasks.
  E) is used to evaluate project costs and benefits.
Title: ________ is a tangible benefit of information systems. A) Improved asset usage B) Reduced ...
Post by: wfdfwc23 on Jul 7, 2018
Answer to Question 1

B

Answer to Question 2

A