Author Question: Establishing cost control is part of the _____ phase. A) bidding B) pre-construction C) ... (Read 25 times)

Anajune7

  • Hero Member
  • *****
  • Posts: 574
Establishing cost control is part of the _____ phase.
 
  A) bidding
  B) pre-construction
  C) construction
  D) closeout

Question 2

Which delivery system involves the owner, architect/engineer, and general contractor?
 
  A) The traditional contract delivery system
  B) The design-build system
  C) The construction management system (CM)
  D) The engineering-procurement-construction (E-P-C) system



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

harveenkau8139

  • Sr. Member
  • ****
  • Posts: 304
Answer to Question 1

Answer: B

Answer to Question 2

Answer: A





 

Did you know?

Bacteria have been found alive in a lake buried one half mile under ice in Antarctica.

Did you know?

The highest suicide rate in the United States is among people ages 65 years and older. Almost 15% of people in this age group commit suicide every year.

Did you know?

The Babylonians wrote numbers in a system that used 60 as the base value rather than the number 10. They did not have a symbol for "zero."

Did you know?

Approximately 25% of all reported medication errors result from some kind of name confusion.

Did you know?

There are 60,000 miles of blood vessels in every adult human.

For a complete list of videos, visit our video library