Author Question: Two of the most important project close-out documents are _____. A) operation and maintenance ... (Read 24 times)

MGLQZ

  • Hero Member
  • *****
  • Posts: 579
Two of the most important project close-out documents are _____.
 
  A) operation and maintenance manuals
  B) certificate of occupancy and record drawings
  C) consent of surety and release of liens
  D) warranties and guarantees

Question 2

The architect/engineer requires that shop drawings be submitted before _____.
 
  A) the pre-bid phase
  B) the pre-construction phase
  C) material and equipment is delivered
  D) the construction phase



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

kjo;oj

  • Sr. Member
  • ****
  • Posts: 328
Answer to Question 1

Answer: C

Answer to Question 2

Answer: C




MGLQZ

  • Member
  • Posts: 579
Reply 2 on: Jul 24, 2018
Thanks for the timely response, appreciate it


  • Member
  • Posts:
Reply 3 on: Yesterday
YES! Correct, THANKS for helping me on my review

 

Did you know?

Allergies play a major part in the health of children. The most prevalent childhood allergies are milk, egg, soy, wheat, peanuts, tree nuts, and seafood.

Did you know?

Persons who overdose with cardiac glycosides have a better chance of overall survival if they can survive the first 24 hours after the overdose.

Did you know?

The first documented use of surgical anesthesia in the United States was in Connecticut in 1844.

Did you know?

More than 20 million Americans cite use of marijuana within the past 30 days, according to the National Survey on Drug Use and Health (NSDUH). More than 8 million admit to using it almost every day.

Did you know?

Cytomegalovirus affects nearly the same amount of newborns every year as Down syndrome.

For a complete list of videos, visit our video library