When using a time-study approach, the standard time is:
◦ the select time multiplied by the rating factor, summed over all work elements.
◦ the normal time per cycle multiplied by 1.0 plus the allowance.
◦ the select time plus z times the standard deviation.
◦ the normal time plus z times the standard deviation.
-
the normal time per cycle multiplied by 1.0 plus the allowance.