Title: HVAC contractors typically use takeoff sheets for air devices and equipment, piping and accessories, ...
Post by: cagreen833 on Jul 24, 2018
HVAC contractors typically use takeoff sheets for air devices and equipment, piping and accessories, and
  _____.
 
  a. raw materials
  b. tools
  c. permits
  d. ductwork

Question 2

Where does a subcontractor usually obtain the submittal information and shop drawings that are used to
  make up a submittal sheet?
 
  a. From the construction project's architect
  b. From previously archived specifications and submittals
  c. From equipment and accessory manufacturers
  d. From relevant schedules and site plans
Title: HVAC contractors typically use takeoff sheets for air devices and equipment, piping and accessories, ...
Post by: Dunkey on Jul 24, 2018
Answer to Question 1

d

Answer to Question 2

c