Title: A firm is planning to set up an assembly line to assemble 40 units per hour, and 57 minutes per hour ...
Post by: Davideckstein7 on Dec 3, 2019
A firm is planning to set up an assembly line to assemble 40 units per hour, and 57 minutes per hour are productive. The time to perform each task and the tasks which precede each task are:

TaskPreceding
Task
Time to perform (min.)
A--.69
BA.55
CB.92
DB.59
EB.70
FB1.10
GC, D, E.75
HG, F.43
IH.29

a. Draw a network diagram of precedence relationships.
b. Compute the required cycle time per unit in minutes.
c. Compute the theoretical minimum number of workstations required to produce 40 units per hour.
d. Balance this line using longest processing time.
e. What is the efficiency of the line obtained in part d?
Title: A firm is planning to set up an assembly line to assemble 40 units per hour, and 57 minutes per hour ...
Post by: yasmin on Dec 3, 2019
(a) The appropriate diagram appears below. (b) Cycle time is 57/40 = 1.425 minutes. (c) The theoretical minimum number of stations required is 6.02/1.425 = 4.22 or 5. (d) The balanced line appears in the software output panel below. (e) The line's efficiency is 6.02 / 8.55 = 70.4%




Station

Task
Time
(minutes)
Time left (minutes)Ready tasks
A
1A0.690.735B
B0.550.185C,D,E,F
2F1.10.325C,D,E
3C0.920.505D,E
4E0.70.725D
D0.590.135G
5G0.750.675H
H0.430.245I
6I0.291.135
Summary Statistics
Cycle time1.425minutes
Time allocated (cycle time ∗ #)8.549999minutes/cycle
Time needed (sum of task times)6.02minutes/unit
Idle time (allocated-needed)2.529999minutes/cycle
Efficiency (needed/allocated)70.40936%
Balance Delay (1-efficiency)29.59064%
Min (theoretical) # of stations5