Previous Image | Next Image |
Description: Oh No!, Inc., sells three models of radar detector units. It buys the three basic models (E, F, and G) from a Japanese manufacturer and adds one, two, or four lights (component D) to further differentiate the models. D is bought from a domestic producer. Picture Lead times are one week for all items except C, which is two weeks. There are ample supplies of the basic units (E, F, and G) on hand. There are also 10 units of B, 10 units of C, and 25 units of D on hand. Lot-sizing rules are lot-for-lot ordering for all items except D, which must be ordered in multiples of 100 units. There is a scheduled receipt of 100 units of D in week 1. The master schedule calls for 40 units of A to be produced at the beginning of week 4, 60 units of B at the beginning of week 5, and 30 units of C at the beginning of week 6. Prepare a material requirements plan for D and its parents. (Leave no cells blank - be certain to enter "0" wherever required.) Parent A: Picture Stats: Views: 380 Filesize: 97.6kB Height: 768 Width: 1366 Source: https://biology-forums.com/index.php?action=gallery;sa=view;id=28127 |