Author Question: A firm has two projects. Project A has an internal rate of return of 6. Project B's internal rate of ... (Read 66 times)

asan beg

  • Hero Member
  • *****
  • Posts: 570
A firm has two projects. Project A has an internal rate of return of 6. Project B's internal rate of return is 11. If the firm's discount rate is 9.57,
 
  A) both projects have a negative net present value.
  B) only project A has a positive net present value.
  C) only project B has a positive net present value.
  D) both projects have a positive net present value.

Question 2

Assel grows mulberry trees. The lumber yard purchases cut trees from you. The trees grow 1 foot per year. Assuming a constant real price per foot for mulberry, at what interest rate would Assel be willing to sell a 10-foot tree today?
 
  A) 3
  B) 5
  C) 8
  D) 12


fauacakatahaias

  • Sr. Member
  • ****
  • Posts: 353
Answer to Question 1

C

Answer to Question 2

D



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Certain chemicals, after ingestion, can be converted by the body into cyanide. Most of these chemicals have been removed from the market, but some old nail polish remover, solvents, and plastics manufacturing solutions can contain these substances.

Did you know?

Excessive alcohol use costs the country approximately $235 billion every year.

Did you know?

Less than one of every three adults with high LDL cholesterol has the condition under control. Only 48.1% with the condition are being treated for it.

Did you know?

Human stomach acid is strong enough to dissolve small pieces of metal such as razor blades or staples.

Did you know?

In most climates, 8 to 10 glasses of water per day is recommended for adults. The best indicator for adequate fluid intake is frequent, clear urination.

For a complete list of videos, visit our video library