Author Question: Activity-based costing, service company. Speediprint Corporation owns a small printing press that ... (Read 864 times)

amal

  • Hero Member
  • *****
  • Posts: 572
Activity-based costing, service company.
 
  Speediprint Corporation owns a small printing press that prints leaflets, brochures, and advertising materials. Speediprint classifies its various printing jobs as standard jobs or special jobs. Speediprint's simple job-costing system has two direct-cost categories (direct materials and direct labor) and a single indirect-cost pool. Speediprint operates at capacity and allocates all indirect costs using printing machine-hours as the allocation base.
   Speediprint is concerned about the accuracy of the costs assigned to standard and special jobs and therefore is planning to implement an activity-based costing system. Speediprint's ABC system would have the same direct-cost categories as its simple costing system. However, instead of a single indirect-cost pool there would now be six categories for assigning indirect costs: design, purchasing, setup, printing machine opera- tions, marketing, and administration. To see how activity-based costing would affect the costs of standard and special jobs, Speediprint collects the following information for the fiscal year 2014 that just ended.
 
  Required:
  1. Calculate the cost of a standard job and a special job under the simple costing system.
  2. Calculate the cost of a standard job and a special job under the activity-based costing system.
  3. Compare the costs of a standard job and a special job in requirements 1 and 2. Why do the simple and activity-based costing systems differ in the cost of a standard job and a special job?
  4. How might Speediprint use the new cost information from its activity-based costing system to better manage its business?

Question 2

Fixed manufacturing overhead variance analysis
 
  The French Bread Company also allocates fixed manufacturing overhead to products on the basis of standard direct manufacturing labor-hours. For 2014, fixed manufacturing overhead was budgeted at 4.00 per direct manufacturing labor-hour. Actual fixed manufacturing overhead incurred during the year was 272,000.
 
  Required:
  1. Prepare a variance analysis of fixed manufacturing overhead cost. Use Exhibit 8- 4 (page 304) as a guide.
  2. Is fixed overhead underallocated or overallocated? By what amount?
  3. Comment on your results. Discuss the variances and explain what may be driving them.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

dellikani2015

  • Sr. Member
  • ****
  • Posts: 332
Answer to Question 1

1. Total indirect costs = 75,000 + 45,000 + 18,000 + 20,000 + 19,500 + 24,000
= 201,500
Total machine-hours = (400 10) + (200 10) = 6,000
Indirect cost rate per machine-hour = 201,500 6,000
= 33.583 per machine-hour

Simple Costing System Standard Job Special Job
Cost of supplies per job 100.00 125.00
Direct labor cost per job 90.00 100.00
Indirect cost allocated to each job
(10 machine hours 33.583 per machine hour)
335.83 335.83
Total costs 525.83 560.83

2. Activity-based costing system
Quantity of Cost Driver Consumed during 2014
(see column (1))

Activity Cost Driver Standard Job Special
Job Total Cost of Activity
(given) Allocation
Rate
(1) (2) (3) (4) (5) (6) = (5) ((3) + (4)), or given

Machine operations
(400 jobs 10 mach. hrs. per job; 200 jobs 10 mach. hrs. per job) machine hours 4,000 2,000 75,000  12.50 per machine hour
Setups (4 400; 7 200)
setup hours 1,600 1,400 45,000  15.00 per setup hour
Purchase orders (given) no. of purchase orders 400 500 18,000  20.00 per purchase order
Design 20,000
Marketing Percentage of revenue 19,500  0.05 per dollar of sales
Administration
(90 400; 100 200)
dir. labor costs 36,000 20,000 24,000 0.42857 per dollar of direct manuf. labor cost

Total Costs
Standard Job Special Job
Cost of supplies (100 400; 125 200)
 40,000  25,000
Direct labor costs (90 400; 100 200)
36,000 20,000
Indirect costs allocated:
Machine operations (12.50 per mach. hr. 4,000; 2,000)
50,000 25,000
Setups (15 per setup hr. 1,600; 1,400)
24,000 21,000
Purchase orders (20 per order 400; 500)
8,000 10,000
Design 4,000 16,000
Marketing (0.05 600 400; 0.05 750 200)
12,000 7,500
Administration (0.42857 36,000; 20,000)
15,429 8,571
Total costs 189,429 133,071
Cost of each job (189,429 400; 133,071 200)
 473.57  665.36

3.
Cost per job Standard Job Special Job
Simple Costing System 525.83 560.83
Activity-based Costing System 473.57 665.36
Difference (Simple  ABC)  52.26  (104.53)

Relative to the ABC system, the simple costing system overcosts standard jobs and undercosts special jobs. Both types of jobs need 10 machine hours per job, so in the simple system, they are each allocated 335.83 in indirect costs. But, the ABC study reveals that each standard job consumes less of the indirect resources such as setups, purchase orders, and design costs than a special job, and this is reflected in the lower indirect costs allocated to the standard jobs and higher indirect costs allocated to special jobs in the ABC system.

4. Speediprint can use the information revealed by the ABC system to change its pricing based on the ABC costs. Under the simple system, Speediprint was making a gross margin of 12 on each standard job (600  525.83 600) and 25 on each special job (750  560.83 750). But, the ABC system reveals that it is actually making a gross margin of 21 (600  473.57 600) on each standard job and about 11 (750  665.36 750) on each special job. Depending on the market competitiveness, Speediprint may either want to reprice the different types of jobs, or it may choose to market standard jobs more aggressively than before.
Speediprint can also use the ABC information to improve its own operations. It could examine each of the indirect cost categories and analyze whether it would be possible to deliver the same level of service, but consume fewer indirect resources, or find a way to reduce the per-unit-cost-driver cost of some of those indirect resources.

Answer to Question 2

1. Budgeted standard direct manufacturing labor used = 0.02 per baguette
Budgeted output = 3,200,000 baguettes
Budgeted standard direct manufacturing labor-hours
= 3,200,000  0.02
= 64,000 hours
Budgeted fixed manufacturing overhead costs
= 64,000  4.00 per hour
= 256,000
Actual output = 2,800,000 baguettes
Allocated fixed manufacturing overhead
= 2,800,000  0.02  4
= 224,000

Fixed Manufacturing Overhead Variance Analysis for French Bread Company for 2014

Actual Costs Incurred
(1)
Same Budgeted
Lump Sum
(as in Static Budget)
Regardless of
Output Level
(2) Flexible Budget:
Same Budgeted
Lump Sum
(as in Static Budget)
Regardless of
Output Level
(3)
Allocated:
Budgeted Input Qty.
Allowed for
Actual Output
 Budgeted Rate
(4)

272,000
256,000
256,000 (2,800,000  0.02  4)
224,000

2. The fixed manufacturing overhead is underallocated by 48,000.

3. The production-volume variance of 32,000 U captures the difference between the budgeted 3,200,0000 baguettes and the lower actual 2,800,000 baguettes producedthe fixed cost capacity not used. The spending variance of 16,000 U means that the actual aggregate of fixed costs (272,000) exceeds the budget amount (256,000). For example, monthly leasing rates for baguette-making machines may have increased above those in the budget for 2014.




amal

  • Member
  • Posts: 572
Reply 2 on: Jul 6, 2018
:D TYSM


fatboyy09

  • Member
  • Posts: 358
Reply 3 on: Yesterday
Wow, this really help

 

Did you know?

On average, someone in the United States has a stroke about every 40 seconds. This is about 795,000 people per year.

Did you know?

Only 12 hours after an egg cell is fertilized by a sperm cell, the egg cell starts to divide. As it continues to divide, it moves along the fallopian tube toward the uterus at about 1 inch per day.

Did you know?

The human body produces and destroys 15 million blood cells every second.

Did you know?

During the twentieth century, a variant of the metric system was used in Russia and France in which the base unit of mass was the tonne. Instead of kilograms, this system used millitonnes (mt).

Did you know?

Interferon was scarce and expensive until 1980, when the interferon gene was inserted into bacteria using recombinant DNA technology, allowing for mass cultivation and purification from bacterial cultures.

For a complete list of videos, visit our video library