Author Question: A(n) ________ is the sequence of activities that determine the earliest date by which aproject can ... (Read 61 times)

folubunmi

  • Hero Member
  • *****
  • Posts: 524
A(n) ________ is the sequence of activities that determine the earliest date by which aproject can be completed.
 
  A) Gantt chart
  B) critical path
  C) encryption algorithm
  D) scatter plot

Question 2

Native mobile applications can be developed by technically oriented Web developers andbusiness professionals.
 
  Indicate whether the statement is true or false



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

perkiness

  • Sr. Member
  • ****
  • Posts: 348
Answer to Question 1

B

Answer to Question 2

FALSE




folubunmi

  • Member
  • Posts: 524
Reply 2 on: Jul 7, 2018
YES! Correct, THANKS for helping me on my review


kilada

  • Member
  • Posts: 311
Reply 3 on: Yesterday
:D TYSM

 

Did you know?

If all the neurons in the human body were lined up, they would stretch more than 600 miles.

Did you know?

According to the CDC, approximately 31.7% of the U.S. population has high low-density lipoprotein (LDL) or "bad cholesterol" levels.

Did you know?

By definition, when a medication is administered intravenously, its bioavailability is 100%.

Did you know?

In 1835 it was discovered that a disease of silkworms known as muscardine could be transferred from one silkworm to another, and was caused by a fungus.

Did you know?

Not getting enough sleep can greatly weaken the immune system. Lack of sleep makes you more likely to catch a cold, or more difficult to fight off an infection.

For a complete list of videos, visit our video library