The SDLC planning phase consists of which activity?
 
  A) Project completion
  B) Project reorganization
  C) Project selection
  D) Project testing

Question 2

Describe the differences between one-time and recurring benefits and costs.
 
  What will be an ideal response?


cegalasso

  • Sr. Member
  • ****
  • Posts: 295
Answer to Question 1

C

Answer to Question 2

One-time costs are costs associated with project start-up and development or system start-up. This type of cost includes hardware and software purchases, user training, and site preparation. Recurring costs are costs resulting from the ongoing evolution and use of a system. New software and hardware leases, incremental communications, and incremental data storage expense are recurring costs.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

The ratio of hydrogen atoms to oxygen in water (H2O) is 2:1.

Did you know?

More than 30% of American adults, and about 12% of children utilize health care approaches that were developed outside of conventional medicine.

Did you know?

Drying your hands with a paper towel will reduce the bacterial count on your hands by 45–60%.

Did you know?

The first oral chemotherapy drug for colon cancer was approved by FDA in 2001.

Did you know?

More than 34,000 trademarked medication names and more than 10,000 generic medication names are in use in the United States.

For a complete list of videos, visit our video library