Author Question: A major outcome and deliverable from the project initiation and planning phase that contains an ... (Read 120 times)

codyclark

  • Hero Member
  • *****
  • Posts: 538
A major outcome and deliverable from the project initiation and planning phase that contains an estimate of the project's scope, benefits, costs, risks, and resource requirements best defines:
 
  A) Baseline Project Plan.
  B) Information Systems Plan.
  C) Business Case.
  D) Statement of Work.
  E) System Service Request.

Question 2

Which of the following slack times indicates that an activity is on the critical path?
 
  A) 1
  B) 10
  C) 0
  D) 2
  E) 5



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

ttt030911

  • Sr. Member
  • ****
  • Posts: 315
Answer to Question 1

A
Explanation: A) The BPP specifies detailed project activities for the next life-cycle phasesystems analysisand provides less detail for subsequent project phases.
CL

Answer to Question 2

C
Explanation: C) An activity on the critical path cannot have a slack time.




codyclark

  • Member
  • Posts: 538
Reply 2 on: Jul 7, 2018
YES! Correct, THANKS for helping me on my review


kusterl

  • Member
  • Posts: 315
Reply 3 on: Yesterday
Gracias!

 

Did you know?

People with alcoholism are at a much greater risk of malnutrition than are other people and usually exhibit low levels of most vitamins (especially folic acid). This is because alcohol often takes the place of 50% of their daily intake of calories, with little nutritional value contained in it.

Did you know?

Cancer has been around as long as humankind, but only in the second half of the twentieth century did the number of cancer cases explode.

Did you know?

The first oncogene was discovered in 1970 and was termed SRC (pronounced "SARK").

Did you know?

There used to be a metric calendar, as well as metric clocks. The metric calendar, or "French Republican Calendar" divided the year into 12 months, but each month was divided into three 10-day weeks. Each day had 10 decimal hours. Each hour had 100 decimal minutes. Due to lack of popularity, the metric clocks and calendars were ended in 1795, three years after they had been first marketed.

Did you know?

Adults are resistant to the bacterium that causes Botulism. These bacteria thrive in honey – therefore, honey should never be given to infants since their immune systems are not yet resistant.

For a complete list of videos, visit our video library