Which of the following is clarified by the project charter?
 
  A) analysis expectations
  B) how much can the scope change before the project will be over budget
  C) the project deliverables
  D) how much will the project cost

Question 2

In the ER Diagram for the SUNSHINE AIRLINE COMPANY, which word should replace BBB?
 
  A) AirplaneTypeID
  B) AIRPLANETYPE
  C) AirportID
  D) AIRPORT



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

ansleighelindsey

  • Sr. Member
  • ****
  • Posts: 364
Answer to Question 1

C

Answer to Question 2

D





 

Did you know?

Pubic lice (crabs) are usually spread through sexual contact. You cannot catch them by using a public toilet.

Did you know?

Fewer than 10% of babies are born on their exact due dates, 50% are born within 1 week of the due date, and 90% are born within 2 weeks of the date.

Did you know?

Today, nearly 8 out of 10 pregnant women living with HIV (about 1.1 million), receive antiretrovirals.

Did you know?

Children of people with alcoholism are more inclined to drink alcohol or use hard drugs. In fact, they are 400 times more likely to use hard drugs than those who do not have a family history of alcohol addiction.

Did you know?

Symptoms of kidney problems include a loss of appetite, back pain (which may be sudden and intense), chills, abdominal pain, fluid retention, nausea, the urge to urinate, vomiting, and fever.

For a complete list of videos, visit our video library