Author Question: A change management program as part of an IT project is used to: A) convert data to useable form. ... (Read 34 times)

soccerdreamer_17

  • Hero Member
  • *****
  • Posts: 552
A change management program as part of an IT project is used to:
 
  A) convert data to useable form.
  B) avoid resistance by business users to a new system being implemented.
  C) help with personnel shifts in a company.
  D) negotiate a contract.

Question 2

Data for executive information systems (EISs) come from both quantitative and qualitative sources.
 
  Indicate whether the statement is true or false



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

zoeyesther

  • Sr. Member
  • ****
  • Posts: 315
Answer to Question 1

B

Answer to Question 2

TRUE





 

Did you know?

Individuals are never “cured” of addictions. Instead, they learn how to manage their disease to lead healthy, balanced lives.

Did you know?

The Romans did not use numerals to indicate fractions but instead used words to indicate parts of a whole.

Did you know?

According to the CDC, approximately 31.7% of the U.S. population has high low-density lipoprotein (LDL) or "bad cholesterol" levels.

Did you know?

There are more bacteria in your mouth than there are people in the world.

Did you know?

Only 12 hours after an egg cell is fertilized by a sperm cell, the egg cell starts to divide. As it continues to divide, it moves along the fallopian tube toward the uterus at about 1 inch per day.

For a complete list of videos, visit our video library