Author Question: The critical path determines the longest time required to complete the project. Indicate whether ... (Read 138 times)

Alygatorr01285

  • Hero Member
  • *****
  • Posts: 564
The critical path determines the longest time required to complete the project.
 
  Indicate whether the statement is true or false

Question 2

The _________ is an optional bit string field used to identify uniquely the issuing CA in the event the X.500 name has been reused for different entities.
 
  What will be an ideal response?



janieazgirl

  • Sr. Member
  • ****
  • Posts: 300
Answer to Question 1

FALSE

Answer to Question 2

issuer unique identifier



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Bacteria have flourished on the earth for over three billion years. They were the first life forms on the planet.

Did you know?

Symptoms of kidney problems include a loss of appetite, back pain (which may be sudden and intense), chills, abdominal pain, fluid retention, nausea, the urge to urinate, vomiting, and fever.

Did you know?

According to the FDA, adverse drug events harmed or killed approximately 1,200,000 people in the United States in the year 2015.

Did you know?

Human neurons are so small that they require a microscope in order to be seen. However, some neurons can be up to 3 feet long, such as those that extend from the spinal cord to the toes.

Did you know?

Certain rare plants containing cyanide include apricot pits and a type of potato called cassava. Fortunately, only chronic or massive ingestion of any of these plants can lead to serious poisoning.

For a complete list of videos, visit our video library