A project with a negative net present value should be:
 A) rejected as it does not take the time value of money into account.
  B) rejected since the expected future cash flows from the project are less than the cost of the investment.
  C) accepted since the net present value does not alter the company's capital budgeting.
  D) accepted since the expected future cash flows from the project exceed the cost of the investment.

Question 2

A limited-liability company extends the concept of personal-asset protection to small business owners.
 
 Indicate whether the statement is true or false



underwood14

  • Sr. Member
  • ****
  • Posts: 346
Answer to Question 1

B

Answer to Question 2

True



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Not getting enough sleep can greatly weaken the immune system. Lack of sleep makes you more likely to catch a cold, or more difficult to fight off an infection.

Did you know?

For pediatric patients, intravenous fluids are the most commonly cited products involved in medication errors that are reported to the USP.

Did you know?

Recent studies have shown that the number of medication errors increases in relation to the number of orders that are verified per pharmacist, per work shift.

Did you know?

In Eastern Europe and Russia, interferon is administered intranasally in varied doses for the common cold and influenza. It is claimed that this treatment can lower the risk of infection by as much as 60–70%.

Did you know?

More than nineteen million Americans carry the factor V gene that causes blood clots, pulmonary embolism, and heart disease.

For a complete list of videos, visit our video library