Author Question: Which of the following is a means of highlighting critical time intervals? a. Delphi b. Gantt ... (Read 13 times)

RODY.ELKHALIL

  • Hero Member
  • *****
  • Posts: 591
Which of the following is a means of highlighting critical time intervals?
 
 

a. Delphi
  b. Gantt
  c. PERT
  d. sensitivity analysis
  e. linear programming



Question 2

Which of the following is not a weakness of planning and decision-making tools?
 
 

a. They may not always adequately reflect reality.
  b. They may be too costly.
  c. Management lacks proper skill in using the tools.
  d. Management resists using the tools.
  e. Management may not have time to use the tools.




Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

patma1981

  • Sr. Member
  • ****
  • Posts: 292
Answer to Question 1

C

Answer to Question 2

E




RODY.ELKHALIL

  • Member
  • Posts: 591
Reply 2 on: Jul 21, 2018
YES! Correct, THANKS for helping me on my review


cassie_ragen

  • Member
  • Posts: 347
Reply 3 on: Yesterday
Great answer, keep it coming :)

 

Did you know?

Parkinson's disease is both chronic and progressive. This means that it persists over a long period of time and that its symptoms grow worse over time.

Did you know?

Normal urine is sterile. It contains fluids, salts, and waste products. It is free of bacteria, viruses, and fungi.

Did you know?

The U.S. Pharmacopeia Medication Errors Reporting Program states that approximately 50% of all medication errors involve insulin.

Did you know?

Street names for barbiturates include reds, red devils, yellow jackets, blue heavens, Christmas trees, and rainbows. They are commonly referred to as downers.

Did you know?

If you could remove all of your skin, it would weigh up to 5 pounds.

For a complete list of videos, visit our video library