Author Question: For a public works project, changes may not be made to any of the documents during which of the ... (Read 30 times)

luvbio

  • Hero Member
  • *****
  • Posts: 623
For a public works project, changes may not be made to any of the documents during which of the following phases?
 
  A. After bid opening, but before award of the contract.
   B. Before opening of bids, but after advertising for bids.
   C. After bid opening, but before signing of the agreement.
   D. After award of the contract, but before signing the agreement.

Question 2

If an engineer does not want to have to write the general conditions of a construction contract where could standard general conditions be purchased?
 
  What will be an ideal response?



xthemafja

  • Sr. Member
  • ****
  • Posts: 348
Answer to Question 1

C

Answer to Question 2

Documents containing standard General Conditions could be purchased from organizations such as the Associated General Contractors, the Construction Management Association of America, the American Institute of Architects, and the Engineers Joint Contracts Documents Committee (EJCDC).



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

In 1835 it was discovered that a disease of silkworms known as muscardine could be transferred from one silkworm to another, and was caused by a fungus.

Did you know?

More than 34,000 trademarked medication names and more than 10,000 generic medication names are in use in the United States.

Did you know?

The first oral chemotherapy drug for colon cancer was approved by FDA in 2001.

Did you know?

Everyone has one nostril that is larger than the other.

Did you know?

When taking monoamine oxidase inhibitors, people should avoid a variety of foods, which include alcoholic beverages, bean curd, broad (fava) bean pods, cheese, fish, ginseng, protein extracts, meat, sauerkraut, shrimp paste, soups, and yeast.

For a complete list of videos, visit our video library