Author Question: The architect/engineer relies on whom for assurance that the monthly estimate of work performed as ... (Read 47 times)

natalie2426

  • Hero Member
  • *****
  • Posts: 524
The architect/engineer relies on whom for assurance that the monthly estimate of work performed as submitted by the contractor is valid?
 
  A. No one, the architect/engineer must verify this.
   B. The contractor whose estimate is guaranteed by a bonding company.
   C. The resident project representative.
   D. The owner.
   E. a notary public.

Question 2

In most states, the parties to a construction contract can agree to resolve disputes through binding arbitration
 
  A. with the consent of the parties only after a dispute actually arises.
   B. at the time of signing the construction contract.
   C. only if neither party chooses to litigate in court.
   D. only on disputes of less than 50,000.
   E. none of the above.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Dominic

  • Sr. Member
  • ****
  • Posts: 328
Answer to Question 1

C

Answer to Question 2

B




natalie2426

  • Member
  • Posts: 524
Reply 2 on: Jul 26, 2018
Thanks for the timely response, appreciate it


Alyson.hiatt@yahoo.com

  • Member
  • Posts: 354
Reply 3 on: Yesterday
Gracias!

 

Did you know?

Multiple experimental evidences have confirmed that at the molecular level, cancer is caused by lesions in cellular DNA.

Did you know?

It is believed that the Incas used anesthesia. Evidence supports the theory that shamans chewed cocoa leaves and drilled holes into the heads of patients (letting evil spirits escape), spitting into the wounds they made. The mixture of cocaine, saliva, and resin numbed the site enough to allow hours of drilling.

Did you know?

Children with strabismus (crossed eyes) can be treated. They are not able to outgrow this condition on their own, but with help, it can be more easily corrected at a younger age. It is important for infants to have eye examinations as early as possible in their development and then another at age 2 years.

Did you know?

The U.S. Pharmacopeia Medication Errors Reporting Program states that approximately 50% of all medication errors involve insulin.

Did you know?

The use of salicylates dates back 2,500 years to Hippocrates’s recommendation of willow bark (from which a salicylate is derived) as an aid to the pains of childbirth. However, overdosage of salicylates can harm body fluids, electrolytes, the CNS, the GI tract, the ears, the lungs, the blood, the liver, and the kidneys and cause coma or death.

For a complete list of videos, visit our video library