The principal steps (not necessarily in proper order) for bidding and contracting for construction are:
A. Open Bids, Award, Agreement, Advertise
B. Agreement, Open Bids, Notice to Proceed, Negotiation
C. Notice to Proceed, Award, Advertising, Opening bids
D. Award, Agreement, Advertising, Notice to Proceed, Open Bids
E. Advertise, Open Bids, Award, Agreement, Preconstruction Conference
Question 2
If a soils report for a potential construction site was prepared under a contract with the owner prior to advertising for bids, indicate which of the following may be properly included in the Contract Documents without excessive risk:
A. log of borings.
B. soils report.
C. subsurface contours.
D. interpretations of subsurface conditions.
E. recommendations of the soils engineer.