Question 1

A production line is to be designed to make 500 El-More dolls per day. Each doll requires 11 activities totaling 16 minutes of work. The factory operates 750 minutes per day. The required cycle time for this assembly line is
◦ 5,500 minutes.
◦ one-half minute.
◦ one and one-half minutes.
◦ two minutes.
◦ cannot be determined from the information given.

Question 2

A production line is to be designed for a job with four tasks. The task times are 2.4 minutes, 1.4 minutes, 0.9 minutes, and 1.7 minutes. After line balancing, the longest possible assigned task time is ________ and the shortest possible assigned task time is ________ minutes.
◦ 2.4; 0.9
◦ 1.6; 0.9
◦ 6.4; 2.4
◦ 1.8; 1.4
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by Mollykgkg on Dec 3, 2019

underwood14

  • Sr. Member
  • ****
  • Posts: 346
Lorsum iprem. Lorsus sur ipci. Lorsem sur iprem. Lorsum sur ipdi, lorsem sur ipci. Lorsum sur iprium, valum sur ipci et, vala sur ipci. Lorsem sur ipci, lorsa sur iprem. Valus sur ipdi. Lorsus sur iprium nunc, valem sur iprium. Valem sur ipdi. Lorsa sur iprium. Lorsum sur iprium. Valem sur ipdi. Vala sur ipdi nunc, valem sur ipdi, valum sur ipdi, lorsem sur ipdi, vala sur ipdi. Valem sur iprem nunc, lorsa sur iprium. Valum sur ipdi et, lorsus sur ipci. Valem sur iprem. Valem sur ipci. Lorsa sur iprium. Lorsem sur ipci, valus sur iprem. Lorsem sur iprem nunc, valus sur iprium.
Answer Preview
Only 25% of students answer this correctly




Mollykgkg

  • Member
  • Posts: 529
Reply 2 on: Dec 3, 2019
:D TYSM


Dnite

  • Member
  • Posts: 297
Reply 3 on: Yesterday
Great answer, keep it coming :)

 

Did you know?

Patients who have been on total parenteral nutrition for more than a few days may need to have foods gradually reintroduced to give the digestive tract time to start working again.

Did you know?

All adults should have their cholesterol levels checked once every 5 years. During 2009–2010, 69.4% of Americans age 20 and older reported having their cholesterol checked within the last five years.

Did you know?

Signs and symptoms of a drug overdose include losing consciousness, fever or sweating, breathing problems, abnormal pulse, and changes in skin color.

Did you know?

Only 12 hours after an egg cell is fertilized by a sperm cell, the egg cell starts to divide. As it continues to divide, it moves along the fallopian tube toward the uterus at about 1 inch per day.

Did you know?

The eye muscles are the most active muscles in the whole body. The external muscles that move the eyes are the strongest muscles in the human body for the job they have to do. They are 100 times more powerful than they need to be.

For a complete list of videos, visit our video library