Author Question: A firm is planning to set up an assembly line to assemble 40 units per hour, and 57 minutes per hour ... (Read 246 times)

leo leo

  • Hero Member
  • *****
  • Posts: 566
A firm is planning to set up an assembly line to assemble 40 units per hour, and 57 minutes per hour are productive. The time to perform each task and the tasks which precede each task are:

TaskPreceding
Task
Time to perform (min.)
A--.69
BA.55
CB.92
DB.59
EB.70
FB1.10
GC, D, E.75
HG, F.43
IH.29

a. Draw a network diagram of precedence relationships.
b. Compute the required cycle time per unit in minutes.
c. Compute the theoretical minimum number of workstations required to produce 40 units per hour.
d. Balance this line using longest processing time.
e. What is the efficiency of the line obtained in part d?


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by leo leo on Dec 3, 2019

Zack0mack0101@yahoo.com

  • Sr. Member
  • ****
  • Posts: 341
Lorsum iprem. Lorsus sur ipci. Lorsem sur iprem. Lorsum sur ipdi, lorsem sur ipci. Lorsum sur iprium, valum sur ipci et, vala sur ipci. Lorsem sur ipci, lorsa sur iprem. Valus sur ipdi. Lorsus sur iprium nunc, valem sur iprium. Valem sur ipdi. Lorsa sur iprium. Lorsum sur iprium. Valem sur ipdi. Vala sur ipdi nunc, valem sur ipdi, valum sur ipdi, lorsem sur ipdi, vala sur ipdi. Valem sur iprem nunc, lorsa sur iprium. Valum sur ipdi et, lorsus sur ipci. Valem sur iprem. Valem sur ipci. Lorsa sur iprium. Lorsem sur ipci, valus sur iprem. Lorsem sur iprem nunc, valus sur iprium.
Answer Preview
Only 25% of students answer this correctly




leo leo

  • Member
  • Posts: 566
Reply 2 on: Dec 3, 2019
Thanks for the timely response, appreciate it


gcook

  • Member
  • Posts: 343
Reply 3 on: Yesterday
Wow, this really help

 

Did you know?

The heart is located in the center of the chest, with part of it tipped slightly so that it taps against the left side of the chest.

Did you know?

Nearly all drugs pass into human breast milk. How often a drug is taken influences the amount of drug that will pass into the milk. Medications taken 30 to 60 minutes before breastfeeding are likely to be at peak blood levels when the baby is nursing.

Did you know?

Although not all of the following muscle groups are commonly used, intramuscular injections may be given into the abdominals, biceps, calves, deltoids, gluteals, laterals, pectorals, quadriceps, trapezoids, and triceps.

Did you know?

Approximately 15–25% of recognized pregnancies end in miscarriage. However, many miscarriages often occur before a woman even knows she is pregnant.

Did you know?

Street names for barbiturates include reds, red devils, yellow jackets, blue heavens, Christmas trees, and rainbows. They are commonly referred to as downers.

For a complete list of videos, visit our video library