Author Question: The project manager should monitor the progress of any activity with a large time variance even if ... (Read 242 times)

mspears3

  • Hero Member
  • *****
  • Posts: 586
The project manager should monitor the progress of any activity with a large time variance even if the expected time does not identify the activity as a critical activity.
  Indicate whether the statement is true or false

Question 2

SSE can never be _____.
 a. larger than SST
  b. smaller than SST
  c. equal to 1
  d. equal to 0



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

cascooper22

  • Sr. Member
  • ****
  • Posts: 312
Answer to Question 1

T

Answer to Question 2

a




mspears3

  • Member
  • Posts: 586
Reply 2 on: Jun 24, 2018
Wow, this really help


epscape

  • Member
  • Posts: 335
Reply 3 on: Yesterday
Gracias!

 

Did you know?

Certain chemicals, after ingestion, can be converted by the body into cyanide. Most of these chemicals have been removed from the market, but some old nail polish remover, solvents, and plastics manufacturing solutions can contain these substances.

Did you know?

More than 4.4billion prescriptions were dispensed within the United States in 2016.

Did you know?

Drugs are in development that may cure asthma and hay fever once and for all. They target leukotrienes, which are known to cause tightening of the air passages in the lungs and increase mucus productions in nasal passages.

Did you know?

It is widely believed that giving a daily oral dose of aspirin to heart attack patients improves their chances of survival because the aspirin blocks the formation of new blood clots.

Did you know?

Asthma is the most common chronic childhood disease in the world. Most children who develop asthma have symptoms before they are 5 years old.

For a complete list of videos, visit our video library