Author Question: Substantial Performance. Grane, a homeowner, contracted with Butkovich & Sons, Inc, to enlarge ... (Read 72 times)

schs14

  • Hero Member
  • *****
  • Posts: 569
Substantial Performance. Grane, a homeowner, contracted with Butkovich & Sons, Inc, to enlarge Grane's basement and build a new room over the remodeled basement area. Butkovich was also to lay a new garage floor and construct a patio. The parties agreed to a price of 19,290 for the work. When the construction was completed, Grane refused to pay the contractor the 9,290 balance he still owed, claiming that Butkovich had failed to install water stops and reinforcing wire in one concrete floor, in accordance with Grane's specifications, and that the main floor of the addition was 8 7/8 inches lower than the plans had called for. Butkovich sued Grane for recovery of the 9,290. As a mortgage holder on the property, the State Bank of St. Charles was named co-defendant by Butkovich, because its interests would be affected by a judgment against Grane if the latter could not pay. Butkovich claimed that it had substantially performed the contract. Grane claimed that performance was of poor quality and that failure to follow contract specifications constituted a material breach. Discuss who should win.

Question 2

The duty of an agent not to mix personal funds with the funds of the principal is the duty:
 a. to account b. of loyalty c. to notify
  d. to perform
  e. none of the other choices, unless instructed not to do this



meganlapinski

  • Sr. Member
  • ****
  • Posts: 333
Answer to Question 1

Substantial performance
The ordinary rule applied in cases involving building contracts is that a builder is not required to perform perfectly. Rather, the builder is held only to a duty of substantial performance. The purchaser who receives substantial performance of a building contract must pay the contract price, less compensation for any deficiencies created by the less than strict performance of the contract. A contractor whose work amounts to less than substantial performance, however, has no right to the contract price; in that situation, the builder's right is, under a theory of quantum meruit, a right to recover only reasonable compensation for value received by the purchaser over and above the injury suffered by the builder's breach. The court held that from the evidence of poor quality and omissions in fulfilling the specifications, it is clear that the plaintiff did not substantially perform the contract. The case was remanded to the trial court to determine the liability of the parties.

Answer to Question 2

a



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

As many as 28% of hospitalized patients requiring mechanical ventilators to help them breathe (for more than 48 hours) will develop ventilator-associated pneumonia. Current therapy involves intravenous antibiotics, but new antibiotics that can be inhaled (and more directly treat the infection) are being developed.

Did you know?

Side effects from substance abuse include nausea, dehydration, reduced productivitiy, and dependence. Though these effects usually worsen over time, the constant need for the substance often overcomes rational thinking.

Did you know?

Women are 50% to 75% more likely than men to experience an adverse drug reaction.

Did you know?

The first war in which wide-scale use of anesthetics occurred was the Civil War, and 80% of all wounds were in the extremities.

Did you know?

Approximately 500,000 babies are born each year in the United States to teenage mothers.

For a complete list of videos, visit our video library