Author Question: ________ are used to identify discrete steps in a process. A) Bar charts B) PERT charts C) CPM ... (Read 86 times)

wrbasek0

  • Hero Member
  • *****
  • Posts: 560
________ are used to identify discrete steps in a process.
 
  A) Bar charts
  B) PERT charts
  C) CPM diagrams
  D) Action plans
  E) Work flow diagrams

Question 2

The ________ is an activity network diagram that is commonly used for construction projects.
 
  A) project planning bar chart
  B) critical path method
  C) program evaluation and review technique
  D) work flow diagram
  E) multi-attribute utility model



wfdfwc23

  • Sr. Member
  • ****
  • Posts: 338
Answer to Question 1

E

Answer to Question 2

B



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

The senior population grows every year. Seniors older than 65 years of age now comprise more than 13% of the total population. However, women outlive men. In the 85-and-over age group, there are only 45 men to every 100 women.

Did you know?

Drug-induced pharmacodynamic effects manifested in older adults include drug-induced renal toxicity, which can be a major factor when these adults are experiencing other kidney problems.

Did you know?

The average human gut is home to perhaps 500 to 1,000 different species of bacteria.

Did you know?

The National Institutes of Health have supported research into acupuncture. This has shown that acupuncture significantly reduced pain associated with osteoarthritis of the knee, when used as a complement to conventional therapies.

Did you know?

In 1835 it was discovered that a disease of silkworms known as muscardine could be transferred from one silkworm to another, and was caused by a fungus.

For a complete list of videos, visit our video library