Author Question: Which of the following tools is most likely to help managers develop a structured process for ... (Read 37 times)

jayhills49

  • Hero Member
  • *****
  • Posts: 559
Which of the following tools is most likely to help managers develop a structured process for evaluating different new product development proposals and deciding which to support?
 
  A) Pareto chart
  B) stage-gate development funnel
  C) critical path method
  D) fishbone diagram

Question 2

A PERT/CAM network is most likely to be used during ________.
 
  A) marketing research
  B) organizational restructuring
  C) project management
  D) organizational value analysis



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

abro1885

  • Sr. Member
  • ****
  • Posts: 337
Answer to Question 1

B

Answer to Question 2

C





 

Did you know?

The human body's pharmacokinetics are quite varied. Our hair holds onto drugs longer than our urine, blood, or saliva. For example, alcohol can be detected in the hair for up to 90 days after it was consumed. The same is true for marijuana, cocaine, ecstasy, heroin, methamphetamine, and nicotine.

Did you know?

Many supplement containers do not even contain what their labels say. There are many documented reports of products containing much less, or more, that what is listed on their labels. They may also contain undisclosed prescription drugs and even contaminants.

Did you know?

Patients who have been on total parenteral nutrition for more than a few days may need to have foods gradually reintroduced to give the digestive tract time to start working again.

Did you know?

The word drug comes from the Dutch word droog (meaning "dry"). For centuries, most drugs came from dried plants, hence the name.

Did you know?

Asthma cases in Americans are about 75% higher today than they were in 1980.

For a complete list of videos, visit our video library