A(n) ________ is the sequence of activities that determine the earliest date by which aproject can be completed.
 
  A) Gantt chart
  B) critical path
  C) encryption algorithm
  D) scatter plot

Question 2

Native mobile applications can be developed by technically oriented Web developers andbusiness professionals.
 
  Indicate whether the statement is true or false



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

perkiness

  • Sr. Member
  • ****
  • Posts: 348
Answer to Question 1

B

Answer to Question 2

FALSE




folubunmi

  • Member
  • Posts: 524
Reply 2 on: Jul 7, 2018
YES! Correct, THANKS for helping me on my review


hollysheppard095

  • Member
  • Posts: 339
Reply 3 on: Yesterday
:D TYSM

 

Did you know?

Approximately 25% of all reported medication errors result from some kind of name confusion.

Did you know?

Nitroglycerin is used to alleviate various heart-related conditions, and it is also the chief component of dynamite (but mixed in a solid clay base to stabilize it).

Did you know?

Normal urine is sterile. It contains fluids, salts, and waste products. It is free of bacteria, viruses, and fungi.

Did you know?

Never take aspirin without food because it is likely to irritate your stomach. Never give aspirin to children under age 12. Overdoses of aspirin have the potential to cause deafness.

Did you know?

Many medications that are used to treat infertility are injected subcutaneously. This is easy to do using the anterior abdomen as the site of injection but avoiding the area directly around the belly button.

For a complete list of videos, visit our video library