Author Question: What is the NPV for a project if its cost of capital is 12 percent and its initial after-tax cost is ... (Read 38 times)

mpobi80

  • Hero Member
  • *****
  • Posts: 519
What is the NPV for a project if its cost of capital is 12 percent and its initial after-tax cost is 5,000,000 and it is expected to provide after-tax operating cash flows of 1,800,000 in year 1,
 
  1,900,000 in year 2, 1,700,000 in year 3, and (1,300,000 ) in year 4?
  A) -1,494,336
  B) 158,011
  C) -158,011
  D) 3,505,664

Question 2

Allocation of the historic costs of fixed assets against the annual revenue they generate is called ________.
 
  A) arbitraging
  B) securitization
  C) depreciation
  D) amortization



memslove

  • Sr. Member
  • ****
  • Posts: 321
Answer to Question 1

A

Answer to Question 2

C



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question


 

Did you know?

Vital signs (blood pressure, temperature, pulse rate, respiration rate) should be taken before any drug administration. Patients should be informed not to use tobacco or caffeine at least 30 minutes before their appointment.

Did you know?

As the western states of America were settled, pioneers often had to drink rancid water from ponds and other sources. This often resulted in chronic diarrhea, causing many cases of dehydration and death that could have been avoided if clean water had been available.

Did you know?

The heart is located in the center of the chest, with part of it tipped slightly so that it taps against the left side of the chest.

Did you know?

It is difficult to obtain enough calcium without consuming milk or other dairy foods.

Did you know?

Approximately 70% of expectant mothers report experiencing some symptoms of morning sickness during the first trimester of pregnancy.

For a complete list of videos, visit our video library