Author Question: One complete set of plans _____. a. is made for all contractors to share b. is kept in the field ... (Read 36 times)

storky111

  • Hero Member
  • *****
  • Posts: 561
One complete set of plans _____.
 
  a. is made for all contractors to share
  b. is kept in the field office for reference
  c. must be on site at all times
  d. must be given to the building inspector

Question 2

The number of drawings in a plan set for a commercial project may be _____.
 
  a. 5 to 10
  b. 10 to 20
  c. 50 to 60
  d. over 100



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

TINA

  • Sr. Member
  • ****
  • Posts: 336
Answer to Question 1

b

Answer to Question 2

c




storky111

  • Member
  • Posts: 561
Reply 2 on: Jul 24, 2018
YES! Correct, THANKS for helping me on my review


ryhom

  • Member
  • Posts: 366
Reply 3 on: Yesterday
Gracias!

 

Did you know?

There are 20 feet of blood vessels in each square inch of human skin.

Did you know?

Approximately 25% of all reported medication errors result from some kind of name confusion.

Did you know?

In 2010, opiate painkllers, such as morphine, OxyContin®, and Vicodin®, were tied to almost 60% of drug overdose deaths.

Did you know?

The average person is easily confused by the terms pharmaceutics and pharmacology, thinking they are one and the same. Whereas pharmaceutics is the science of preparing and dispensing drugs (otherwise known as the science of pharmacy), pharmacology is the study of medications.

Did you know?

Only one in 10 cancer deaths is caused by the primary tumor. The vast majority of cancer mortality is caused by cells breaking away from the main tumor and metastasizing to other parts of the body, such as the brain, bones, or liver.

For a complete list of videos, visit our video library