Author Question: Since virtually all major construction scheduling tasks are now performed with the use of scheduling ... (Read 41 times)

ts19998

  • Hero Member
  • *****
  • Posts: 531
Since virtually all major construction scheduling tasks are now performed with the use of scheduling software on personal computers, why are manual computations still taught in scheduling classes?
 
  What will be an ideal response?

Question 2

Describe the type of information that an as-built schedule can provide to a firm that might not otherwise be obtained.
 
  What will be an ideal response?



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

JaynaD87

  • Sr. Member
  • ****
  • Posts: 368
Answer to Question 1

There are different ways that computer programs can be set up. To that end, the
information provided by them can be derived by different means and the information may
not always be consistent between programs. In order for this to not be an obstacle, it is
important that the user of the information has a clear understanding of the means by
which the information was obtained. This understanding may well be lacking if the user
cannot independently generate the same information. This is not to say that the user must
verify the scheduling output, but the user must be able to critically assess the information.
This will not be a task readily performed if the user does not have a very good
understanding of the scheduling process, especially the manual computations.

Answer to Question 2

As-built schedules are after-the-fact portrayals of how a project was actually
constructed in terms of sequencing of activities and the dates over which they were
performed. While the sequencing may change somewhat from the as-planned or original
schedule, the information of particular value will relate to when activities were actually
begun and how long they took to complete. This information has various uses. Just as
cost information is valuable for making estimates on future projects, schedule
information is valuable to both schedulers and estimators when new projects are being
considered. Thus, future schedules may be more accurate when based on actual schedule
data from prior projects. As-built schedules are also very useful when disputes arise as
they can help to show how various types of occurrences (changes, delays, suspensions,
changed conditions, etc.) adversely impacted progress on a project.




ts19998

  • Member
  • Posts: 531
Reply 2 on: Jul 26, 2018
Great answer, keep it coming :)


ultraflyy23

  • Member
  • Posts: 312
Reply 3 on: Yesterday
Gracias!

 

Did you know?

In 1835 it was discovered that a disease of silkworms known as muscardine could be transferred from one silkworm to another, and was caused by a fungus.

Did you know?

The first monoclonal antibodies were made exclusively from mouse cells. Some are now fully human, which means they are likely to be safer and may be more effective than older monoclonal antibodies.

Did you know?

Drugs are in development that may cure asthma and hay fever once and for all. They target leukotrienes, which are known to cause tightening of the air passages in the lungs and increase mucus productions in nasal passages.

Did you know?

A headache when you wake up in the morning is indicative of sinusitis. Other symptoms of sinusitis can include fever, weakness, tiredness, a cough that may be more severe at night, and a runny nose or nasal congestion.

Did you know?

The first oral chemotherapy drug for colon cancer was approved by FDA in 2001.

For a complete list of videos, visit our video library