According to the manufacturing framework, what is the immediate preceding process that provides input for the MPS process?
 a. MRP c. Demand Management
  b. S&OP d. Aggregate Planning

Question 2

In order to determine the p-value, which of the following is not needed?
 a. The level of significance
  b. Whether the test is one or two tail
  c. The value of the test statistic
  d. All of these are needed.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

medine

  • Sr. Member
  • ****
  • Posts: 344
Answer to Question 1

D

Answer to Question 2

A



drink

  • Hero Member
  • *****
  • Posts: 554
Both answers were spot on, thank you once again



medine

  • Sr. Member
  • ****
  • Posts: 344

 

Did you know?

Barbituric acid, the base material of barbiturates, was first synthesized in 1863 by Adolph von Bayer. His company later went on to synthesize aspirin for the first time, and Bayer aspirin is still a popular brand today.

Did you know?

Egg cells are about the size of a grain of sand. They are formed inside of a female's ovaries before she is even born.

Did you know?

If you use artificial sweeteners, such as cyclamates, your eyes may be more sensitive to light. Other factors that will make your eyes more sensitive to light include use of antibiotics, oral contraceptives, hypertension medications, diuretics, and antidiabetic medications.

Did you know?

On average, someone in the United States has a stroke about every 40 seconds. This is about 795,000 people per year.

Did you know?

Elderly adults are living longer, and causes of death are shifting. At the same time, autopsy rates are at or near their lowest in history.

For a complete list of videos, visit our video library