Question 1
The conference method estimates cost functions ________.
◦ using quantitative methods that can be very time consuming and costly
◦ based on analysis and opinions gathered from various departments
◦ using time-and-motion studies
◦ by mathematically analyzing the relationship between inputs and outputs in physical terms
Question 2
Variable cost per labor-hour is $0.82 Fixed cost is $18,500. Machine hours during the period are 90. Calculate the total cost for 360 labor hours.
◦ $18,574
◦ $18,795
◦ $18,869
◦ $369