For an activity with more than one immediate predecessor activity, which of the following is used to compute its earliest finish (EF) time?
 a. the largest EF among the immediate predecessors.
  b. the average EF among the immediate predecessors.
  c. the largest LF among the immediate predecessors.
  d. the difference in EF among the immediate predecessors.

Question 2

The interval estimate of the mean value of y for a given value of x is the _____.
 a. confidence interval
  b. prediction interval
  c. residual interval
  d. correlation interval



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

leahchrapun

  • Sr. Member
  • ****
  • Posts: 332
Answer to Question 1

A

Answer to Question 2

a




Yolanda

  • Member
  • Posts: 757
Reply 2 on: Jun 24, 2018
:D TYSM


steff9894

  • Member
  • Posts: 337
Reply 3 on: Yesterday
Great answer, keep it coming :)

 

Did you know?

By definition, when a medication is administered intravenously, its bioavailability is 100%.

Did you know?

Intradermal injections are somewhat difficult to correctly administer because the skin layers are so thin that it is easy to accidentally punch through to the deeper subcutaneous layer.

Did you know?

Increased intake of vitamin D has been shown to reduce fractures up to 25% in older people.

Did you know?

More than 150,000 Americans killed by cardiovascular disease are younger than the age of 65 years.

Did you know?

The U.S. Preventive Services Task Force recommends that all women age 65 years of age or older should be screened with bone densitometry.

For a complete list of videos, visit our video library