This topic contains a solution. Click here to go to the answer

Author Question: For an activity with more than one immediate predecessor activity, which of the following is used to ... (Read 104 times)

Yolanda

  • Hero Member
  • *****
  • Posts: 757
For an activity with more than one immediate predecessor activity, which of the following is used to compute its earliest finish (EF) time?
 a. the largest EF among the immediate predecessors.
  b. the average EF among the immediate predecessors.
  c. the largest LF among the immediate predecessors.
  d. the difference in EF among the immediate predecessors.

Question 2

The interval estimate of the mean value of y for a given value of x is the _____.
 a. confidence interval
  b. prediction interval
  c. residual interval
  d. correlation interval



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

leahchrapun

  • Sr. Member
  • ****
  • Posts: 332
Answer to Question 1

A

Answer to Question 2

a




Yolanda

  • Member
  • Posts: 757
Reply 2 on: Jun 24, 2018
YES! Correct, THANKS for helping me on my review


laurnthompson

  • Member
  • Posts: 334
Reply 3 on: Yesterday
Gracias!

 

Did you know?

Anti-aging claims should not ever be believed. There is no supplement, medication, or any other substance that has been proven to slow or stop the aging process.

Did you know?

Approximately one in four people diagnosed with diabetes will develop foot problems. Of these, about one-third will require lower extremity amputation.

Did you know?

Medication errors are more common among seriously ill patients than with those with minor conditions.

Did you know?

Bacteria have flourished on the earth for over three billion years. They were the first life forms on the planet.

Did you know?

About 100 new prescription or over-the-counter drugs come into the U.S. market every year.

For a complete list of videos, visit our video library