Author Question: When activity times are uncertain, a. assume they are normally distributed. b. calculate the ... (Read 154 times)

michelleunicorn

  • Hero Member
  • *****
  • Posts: 565
When activity times are uncertain,
 a. assume they are normally distributed.
  b. calculate the expected time, using (a + 4m + b)/6.
  c. use the most likely time.
  d. calculate the expected time, using (a + m + b)/3.

Question 2

In a residual plot against x that does NOT suggest we should challenge the assumptions of our regression model, we would expect to see a _____.
 a. horizontal band of points centered near 0
  b. widening band of points
  c. band of points having a slope consistent with that of the regression equation
  d. parabolic band of points



brbarasa

  • Sr. Member
  • ****
  • Posts: 308
Answer to Question 1

B

Answer to Question 2

a



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

About 3% of all pregnant women will give birth to twins, which is an increase in rate of nearly 60% since the early 1980s.

Did you know?

The Centers for Disease Control and Prevention has released reports detailing the deaths of infants (younger than 1 year of age) who died after being given cold and cough medications. This underscores the importance of educating parents that children younger than 2 years of age should never be given over-the-counter cold and cough medications without consulting their physicians.

Did you know?

The horizontal fraction bar was introduced by the Arabs.

Did you know?

If all the neurons in the human body were lined up, they would stretch more than 600 miles.

Did you know?

Oliver Wendell Holmes is credited with introducing the words "anesthesia" and "anesthetic" into the English language in 1846.

For a complete list of videos, visit our video library