When activity times are uncertain,
 a. assume they are normally distributed.
  b. calculate the expected time, using (a + 4m + b)/6.
  c. use the most likely time.
  d. calculate the expected time, using (a + m + b)/3.

Question 2

In a residual plot against x that does NOT suggest we should challenge the assumptions of our regression model, we would expect to see a _____.
 a. horizontal band of points centered near 0
  b. widening band of points
  c. band of points having a slope consistent with that of the regression equation
  d. parabolic band of points



brbarasa

  • Sr. Member
  • ****
  • Posts: 308
Answer to Question 1

B

Answer to Question 2

a



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Your chance of developing a kidney stone is 1 in 10. In recent years, approximately 3.7 million people in the United States were diagnosed with a kidney disease.

Did you know?

All patients with hyperparathyroidism will develop osteoporosis. The parathyroid glands maintain blood calcium within the normal range. All patients with this disease will continue to lose calcium from their bones every day, and there is no way to prevent the development of osteoporosis as a result.

Did you know?

Recent studies have shown that the number of medication errors increases in relation to the number of orders that are verified per pharmacist, per work shift.

Did you know?

The effects of organophosphate poisoning are referred to by using the abbreviations “SLUD” or “SLUDGE,” It stands for: salivation, lacrimation, urination, defecation, GI upset, and emesis.

Did you know?

Parkinson's disease is both chronic and progressive. This means that it persists over a long period of time and that its symptoms grow worse over time.

For a complete list of videos, visit our video library