Author Question: Arcs in a project network indicate a. completion times. b. precedence relationships. c. ... (Read 127 times)

nenivikky

  • Hero Member
  • *****
  • Posts: 516
Arcs in a project network indicate
 a. completion times.
  b. precedence relationships.
  c. activities.
  d. the critical path.

Question 2

An ANOVA procedure is used for data obtained from four populations. Four samples, each comprised of 30 observations, were taken from the four populations. The numerator and denominator (respectively) degrees of freedom for the critical value of F are _____.
 a. 3 and 30
  b. 4 and 30
  c. 3 and 119
  d. 3 and 116



C.mcnichol98

  • Sr. Member
  • ****
  • Posts: 314
Answer to Question 1

B

Answer to Question 2

d



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Approximately 500,000 babies are born each year in the United States to teenage mothers.

Did you know?

The shortest mature adult human of whom there is independent evidence was Gul Mohammed in India. In 1990, he was measured in New Delhi and stood 22.5 inches tall.

Did you know?

During pregnancy, a woman is more likely to experience bleeding gums and nosebleeds caused by hormonal changes that increase blood flow to the mouth and nose.

Did you know?

Earwax has antimicrobial properties that reduce the viability of bacteria and fungus in the human ear.

Did you know?

In ancient Rome, many of the richer people in the population had lead-induced gout. The reason for this is unclear. Lead poisoning has also been linked to madness.

For a complete list of videos, visit our video library