Author Question: ________ is an analytical method that determines the probabilities of the project completion times ... (Read 70 times)

lunatika

  • Hero Member
  • *****
  • Posts: 548
________ is an analytical method that determines the probabilities of the project completion times in project management models by assuming that the expected activity times define the critical path and that the distribution of project completion time
 
  is normal using the central limit theorem.A) Program Estimation and Research Technique
  B) Project Evaluation and Revise Technique
  C) Program Evaluation and Review Technique
  D) Project Estimation and Risk Technique

Question 2

Calculate the total number of television sets shipped from the plant in Arizona. (Hint: Use Solver)
 
  A) 1400 units
  B) 1350 units
  C) 1300 units
  D) 1250 units


zoeyesther

  • Sr. Member
  • ****
  • Posts: 315
Answer to Question 1

C

Answer to Question 2

D



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question


 

Did you know?

During the twentieth century, a variant of the metric system was used in Russia and France in which the base unit of mass was the tonne. Instead of kilograms, this system used millitonnes (mt).

Did you know?

Excessive alcohol use costs the country approximately $235 billion every year.

Did you know?

Allergies play a major part in the health of children. The most prevalent childhood allergies are milk, egg, soy, wheat, peanuts, tree nuts, and seafood.

Did you know?

Studies show that systolic blood pressure can be significantly lowered by taking statins. In fact, the higher the patient's baseline blood pressure, the greater the effect of statins on his or her blood pressure.

Did you know?

Throughout history, plants containing cardiac steroids have been used as heart drugs and as poisons (e.g., in arrows used in combat), emetics, and diuretics.

For a complete list of videos, visit our video library