Author Question: ________ is an analytical method that determines the probabilities of the project completion times ... (Read 75 times)

lunatika

  • Hero Member
  • *****
  • Posts: 548
________ is an analytical method that determines the probabilities of the project completion times in project management models by assuming that the expected activity times define the critical path and that the distribution of project completion time
 
  is normal using the central limit theorem.A) Program Estimation and Research Technique
  B) Project Evaluation and Revise Technique
  C) Program Evaluation and Review Technique
  D) Project Estimation and Risk Technique

Question 2

Calculate the total number of television sets shipped from the plant in Arizona. (Hint: Use Solver)
 
  A) 1400 units
  B) 1350 units
  C) 1300 units
  D) 1250 units


zoeyesther

  • Sr. Member
  • ****
  • Posts: 315
Answer to Question 1

C

Answer to Question 2

D



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question


 

Did you know?

By definition, when a medication is administered intravenously, its bioavailability is 100%.

Did you know?

The longest a person has survived after a heart transplant is 24 years.

Did you know?

There used to be a metric calendar, as well as metric clocks. The metric calendar, or "French Republican Calendar" divided the year into 12 months, but each month was divided into three 10-day weeks. Each day had 10 decimal hours. Each hour had 100 decimal minutes. Due to lack of popularity, the metric clocks and calendars were ended in 1795, three years after they had been first marketed.

Did you know?

Interferon was scarce and expensive until 1980, when the interferon gene was inserted into bacteria using recombinant DNA technology, allowing for mass cultivation and purification from bacterial cultures.

Did you know?

Sperm cells are so tiny that 400 to 500 million (400,000,000–500,000,000) of them fit onto 1 tsp.

For a complete list of videos, visit our video library