________ is an analytical method that determines the probabilities of the project completion times in project management models by assuming that the expected activity times define the critical path and that the distribution of project completion time
 
  is normal using the central limit theorem.A) Program Estimation and Research Technique
  B) Project Evaluation and Revise Technique
  C) Program Evaluation and Review Technique
  D) Project Estimation and Risk Technique

Question 2

Calculate the total number of television sets shipped from the plant in Arizona. (Hint: Use Solver)
 
  A) 1400 units
  B) 1350 units
  C) 1300 units
  D) 1250 units


zoeyesther

  • Sr. Member
  • ****
  • Posts: 315
Answer to Question 1

C

Answer to Question 2

D



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question


 

Did you know?

Approximately 500,000 babies are born each year in the United States to teenage mothers.

Did you know?

In 1835 it was discovered that a disease of silkworms known as muscardine could be transferred from one silkworm to another, and was caused by a fungus.

Did you know?

Blood is approximately twice as thick as water because of the cells and other components found in it.

Did you know?

As many as 28% of hospitalized patients requiring mechanical ventilators to help them breathe (for more than 48 hours) will develop ventilator-associated pneumonia. Current therapy involves intravenous antibiotics, but new antibiotics that can be inhaled (and more directly treat the infection) are being developed.

Did you know?

Most fungi that pathogenically affect humans live in soil. If a person is not healthy, has an open wound, or is immunocompromised, a fungal infection can be very aggressive.

For a complete list of videos, visit our video library