Author Question: Recently a shipping company took 30 samples, each of size n = 100, of packages that it was ... (Read 61 times)

mikaylakyoung

  • Hero Member
  • *****
  • Posts: 531
Recently a shipping company took 30 samples, each of size n = 100, of packages that it was responsible for delivering. Out of the 3,000 total packages, 300 were delivered late.
 
  In setting up an appropriate process control chart, what would be the correct 3-sigma upper control limit value?A) 0.03
  B) 0.13
  C) 0.19
  D) 0.07

Question 2

If a company has 12 years of annual sales data and is in need of a three-year forecast, which of the following forecasting techniques might be useful?
 
  A) Forecast generalization
  B) Seasonality processing
  C) Regression-based trend forecasting
  D) Random component analysis



IAPPLET

  • Sr. Member
  • ****
  • Posts: 333
Answer to Question 1

C

Answer to Question 2

C



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

People with high total cholesterol have about two times the risk for heart disease as people with ideal levels.

Did you know?

The word drug comes from the Dutch word droog (meaning "dry"). For centuries, most drugs came from dried plants, hence the name.

Did you know?

When blood is deoxygenated and flowing back to the heart through the veins, it is dark reddish-blue in color. Blood in the arteries that is oxygenated and flowing out to the body is bright red. Whereas arterial blood comes out in spurts, venous blood flows.

Did you know?

Critical care patients are twice as likely to receive the wrong medication. Of these errors, 20% are life-threatening, and 42% require additional life-sustaining treatments.

Did you know?

Approximately 15–25% of recognized pregnancies end in miscarriage. However, many miscarriages often occur before a woman even knows she is pregnant.

For a complete list of videos, visit our video library