Author Question: In a PERT network, a/an _____ is the earliest time a project can finish given the expected activity ... (Read 60 times)

fnuegbu

  • Hero Member
  • *****
  • Posts: 539
In a PERT network, a/an _____ is the earliest time a project can finish given the expected activity time.
 a. late finish
 b. on time start
 c. on time finish
  d. early start
 e. early finish

Question 2

According to the financial approach, choosing a channel structure is analogous to:
 a. Aspinwall's parallel systems approach.
  b. An investment decision of capital budgeting.
  c. Most of the management science approaches.
  d. The Bayesian approach to channel choice.
  e. Simulations of channel choice decisions.



Viet Thy

  • Sr. Member
  • ****
  • Posts: 329
Answer to Question 1

e

Answer to Question 2

B



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Children with strabismus (crossed eyes) can be treated. They are not able to outgrow this condition on their own, but with help, it can be more easily corrected at a younger age. It is important for infants to have eye examinations as early as possible in their development and then another at age 2 years.

Did you know?

On average, the stomach produces 2 L of hydrochloric acid per day.

Did you know?

Drug abusers experience the following scenario: The pleasure given by their drug (or drugs) of choice is so strong that it is difficult to eradicate even after years of staying away from the substances involved. Certain triggers may cause a drug abuser to relapse. Research shows that long-term drug abuse results in significant changes in brain function that persist long after an individual stops using drugs. It is most important to realize that the same is true of not just illegal substances but alcohol and tobacco as well.

Did you know?

Most women experience menopause in their 50s. However, in 1994, an Italian woman gave birth to a baby boy when she was 61 years old.

Did you know?

Though newer “smart” infusion pumps are increasingly becoming more sophisticated, they cannot prevent all programming and administration errors. Health care professionals that use smart infusion pumps must still practice the rights of medication administration and have other professionals double-check all high-risk infusions.

For a complete list of videos, visit our video library