Author Question: In a PERT network, a/an _____ is the earliest point in time an activity can begin. a. late start b. ... (Read 79 times)

DelorasTo

  • Hero Member
  • *****
  • Posts: 548
In a PERT network, a/an _____ is the earliest point in time an activity can begin.
 a. late start
 b. on time start
  c. early finish
 d. early start
 e. late finish

Question 2

According to Aspinwall, short channels are expected for products with a:
 a. High replacement rate.
  b. High gross margin.
  c. Low time of consumption.
  d. Low adjustment needs.
  e. Low searching time.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Jossy

  • Sr. Member
  • ****
  • Posts: 336
Answer to Question 1

d

Answer to Question 2

B




DelorasTo

  • Member
  • Posts: 548
Reply 2 on: Jun 29, 2018
Thanks for the timely response, appreciate it


Laurenleakan

  • Member
  • Posts: 309
Reply 3 on: Yesterday
YES! Correct, THANKS for helping me on my review

 

Did you know?

There are more nerve cells in one human brain than there are stars in the Milky Way.

Did you know?

Normal urine is sterile. It contains fluids, salts, and waste products. It is free of bacteria, viruses, and fungi.

Did you know?

Everyone has one nostril that is larger than the other.

Did you know?

Pregnant women usually experience a heightened sense of smell beginning late in the first trimester. Some experts call this the body's way of protecting a pregnant woman from foods that are unsafe for the fetus.

Did you know?

Intradermal injections are somewhat difficult to correctly administer because the skin layers are so thin that it is easy to accidentally punch through to the deeper subcutaneous layer.

For a complete list of videos, visit our video library